Mount Holly Culvert Replacement & Slope Stabilization

Client: Mount Holly, VT
Project Span: 2018-2019

PROJECT OVERVIEW

EIV managed landscape inspection and public relations for this $1.6M project located along a .1-mile portion of Route 155 in the town of Mount Holly. Project elements included roadway construction, culvert replacements and steep embankment stabilization. Environmental elements included the installation of over 30 tree trunks which were placed into the side of the slope for increased stabilization. EIV’s arborist inspected the installation of over 600 native trees and shrubs in plant pockets along the slope. This is a first-time approach for a bioengineered slope stabilization of this scale in Vermont.